MANAGER’S REPORT
12 May. 2009
Spring
time in
That is the good news – the bad news is that COID and the other irrigation districts in the Deschutes Basin Board of Control were not awarded the applied for Habitat Conservation Plan (HCP) grant. The grant request was for the necessary funding to carry on the HCP effort past September of this year. This was obviously disappointing news that may negatively effect the progress of the last two years. Increased grant requests around the country and reduced funding availability for this program contributed to the situation. COID and the DBBC is working with our Congressional delegation and State and Regional officials from the US Fish & Wildlife Service for alternative funding to keep the process going forward. The next grant filings can take place in September 2009 for awards expected in the spring of 2010.
The National Oceanic and Atmospheric Administration (NOAA) announced at the HCP Stakeholder meeting held in Prineville on April 27th that a draft 10j Rule is expected to be issued early this summer. If successfully implemented, this rule will classify the reintroduced steelhead as “experimental, non-essential” but still be listed as threatened. While the steelhead may carry experimental, non-essential status, it is likely only for an intermediate term of time. This time will be critical for the irrigation districts to continue pursuing conservation projects and mitigate any potential negative effects their diversions may have on the steelhead.
The
federal economic stimulus package picture continues to develop for COID’s
Juniper Ridge Piping and Hydroelectric Project scheduled to begin construction
in October 2009. Several other
irrigation districts in
The administrative beginnings of the land exchange with BLM endorsed within the Public Lands Bill creating the Badlands Wilderness has barely begun. The process of the exchange may take up to two years for completion pending surveys and other transaction details. This effort will be the responsibility of BLM.
The State legislature has until next week for all bills to have passed out of their initial committee or they are “dead”. The budget shortfall in funding along with a number of other issues are driving a fast pace for the legislature. There are many bills dealing with water and land use still alive and still receiving the attention of COID and the other irrigation districts of the Oregon Water Resource Congress.
The Juniper Ridge Hydroelectric and Piping Project is continuing on schedule. May 1st was the deadline to receive bids on the project. As anticipated a total of five (5) bids were deemed complete and officially received. Review of the bids has commenced with a ranking of the bids completed. It is anticipated that a project team will be officially selected by the Board of Directors by May 15. Construction will begin in early October 2009 with completion of the piping by April 2, 2010 and the hydro facility up and running by late summer 2010.
The opportunities pursued this past month include, but are not limited to:
·
· The Deschutes Water Alliance (DWA) is moving forward with Water Bank transactions and planning for 2009. There is movement to expand active participation of the counties and elected officials and to formalize the partners’ relationships with memorandums of understanding or other forms of agreement for existing and future coordination on regional water issues.
· Kevin Crew with Black Rock Consulting is facilitating the process for a 20 Year District Capital Improvement Plan (CIP). Preliminary evaluations and data gathering are already underway with staff coordination and information on the entire irrigation system. A draft concept is anticipated for Board discussion this winter.
·
COID and four other irrigation districts are
continuing their work with City of
·
COID has re-engaged Pacific Power in
conversations over termination of their lease and hydro facility at
· COID is coordinating with BLM staff on operational issues involving BLM owned and COID owned lands and where COID has federal 1891 Rights of Way.
· COID is coordinating discussions between the US Forest Service and the Bureau of Reclamation on clarifying operational boundaries at the Crane Prairie Dam.
The challenges presenting themselves:
·
The issue of the gates placed without COID
approval on the canal ditch road in southeast
STATUS REPORT
Juniper
Ridge Piping & Hydroelectric Project
· Pre-Proposal meeting with potential bidders on March 10
· Submitted grant application to OWEB with Deschutes River Conservancy for $3.75 MM.
· ODOE Small Energy Loan Program application submitted along with pursuit of commercial and federal loan guarantee financing. ODOE loans carry only a revenue obligation of the project and can not encumber patron assessments.
· Business Energy Tax Credit application submitted in early February
· DEQ State Revolving Fund application accepted. Ranked #5 project in state for funding – funding request $5million. $2.5 MM in grant and $2.5MM in 20 year 0% interest loan.
· FERC and State permit application to be submitted after natural resource consultations completed in late April
·
City of
· Federal economic stimulus funding thru Bureau of Reclamation request of $5 million pending. Notification expected early summer.
Status – proceeding
State Legislature
· Legislative effort to make renewable energy projects completed before 1995, including COID’s Siphon Power Project to be eligible for Renewable Energy Credits (RECs) under the State’s Renewable Portfolio Standard. Senate Bill 743 has a scheduled hearing on April 14. COID testified in support.
· Legislative effort to eliminate possible liability issues with the recreational use of easements and rights of way. Original legislative concept proposed by COID. Bill introduced HB 2879 with first hearing completed and amendments pending.
· HB 2227 dealing with Destination Resorts passed committee to be scheduled for House vote. Amendment 7 was also passed by committee and prohibits Destination Resorts within irrigation district boundaries.
· SB 788 will implement fees on all groundwater wells with a permit or exempt. In addition, a fee will be placed on surface water certificates to assist in funding critical functions of the Oregon Water Resource Department (OWRD).
Status – all bills
proceeding
Deschutes
Water
·
Draft memorandum of understanding under review
by DWA members. It is expected that all
three counties, cities, irrigation districts and others will be asked to
consider signing the MOU and become engaged in the regional water discussion
and planning efforts.
·
Status – In process
· Cooperative
evaluation of potential 50-100 acre re-regulating structure on
Status
– In Process with no change in last month
Real
Estate
· One 20 acre
parcel near
Status – In Process with no change in last month
· COID and
the
·
The cities of
Status – In Process. Joint meetings being conducted with
City of
·
A Conditional
Use permit was received for COID owned lands along
Status – In Process with no change in last month
· Presentation and formal proposal prepared for the annual Mount Bachelor Village Homeowners Association annual meeting for April 25 was cancelled. Efforts to address COID request on scenic easement to allow for development of limited acreage will continue.
Status – On Hold
Development
· Direct communication with City of Bend and Redmond public works and planning staff on resolving issues of canal safety and impacts of development that will require piping.
Status – In Process.
Preliminary discussions held, issues ongoing, no resolution expected for
some time.
ON THE RADAR SCREEN
· Bull Trout Draft Recovery Plan
· Pursuit of funding designations with Bonneville Power Administration for conservation projects above Pelton Round Butte complex